Value: 15 points

 

 

Perform a conceptual estimate for a 355,000 sf office building to be constructed in Phoenix, AZ.  The building will be completed in September 2020.

 

As a comparable you have identified a building with the following characteristics:

  • Size: 305,210 sf
  • Location: Denver, CO
  • Completion Date: June 2001
  • Cost: $36,679,378

 

Using indices below, adjust for size, time, and location to find the conceptual estimate cost for the new building to be built in Phoenix, AZ.

 

Time Factors:

  • Jun2001 = 3572
  • Nov 2015 = 5510

Location Factors:

  • Phoenix, AZ = 88.7
  • Denver, CO = 94.3

Size Factors: (See attached table)

 

 

 

 

 

 